In a job shop, effective capacity is only 45 percent of design capacity, and actual output is 73 percent of effective output. What design capacity would be needed to achieve an actual output of 11 jobs per week? What is its effective capacity?

The Design Capacity needed to achieve the required actual job outputs?

The Effective Capacity needed to achieve the required actual job outputs?

 